Ship Loader Luff Cylinder Replacement
Working against the elements and 2km off land with limited access, the Tidal team accomplished the works with time to spare.
Working against the elements and 2km off land with limited access, the Tidal team accomplished the works with time to spare.
This project saw our project team replace an exhaust fan at a prominent underground mining operation in the Goldfields.
Significant engineering was required to ensure machine stability during change out. The reclaimer had a two-piece hinged boom.
The client required nine (9) separate platforms for rear access to established resister cabinets to allow safe and secure access.
Conveyor required upgrading from 2,050 tonnes per hour to 3,000 tonnes per hour in order to meet current demand.
The client’s vessel had sustained considerable cyclone damage to the hull and was partially submerged.