Ship Loader Luff Cylinder Replacement

Client: Iron Ore Operation
Project: Ship Loader Luff Cylinder Replacement
Location: Pilbara
Project Highlights:

The cylinders were last changed out around 15 – 20 years ago but this project was the first time they had been changed out in a single shutdown. Working against the elements including strong winds, among other work groups and 2km off land with limited access, the Tidal team accomplished the works with time to spare.

“Tidal Solutions project crew were a pleasure to work with, quality people and quality workmanship.”

“Not only was the work completed safely it was also way ahead of schedule giving us some valuable ship loading time back.”

– Major Works Planner