Screenhouse conveyor upgrade

10M Conveyor UpgradeĀ 

Client: Rio Tinto
Project: 10M Conveyor Upgrade
Location: Tom Price Minesite, WA
Project Highlights: 10M Conveyor Upgrade

Conveyor required upgrading from 2,050 tonnes per hour to 3,000 tonnes per hour in order to meet current demand. Tidal Solutions managed the entire brownfield project fabrication, installation and commissioning for the project.

Issues addressed and resolved

This project presented a unique challenge to complete the required work with minimal production impact. Tidal Solutions completed the project within project timelines and budget with no HSE incidents or accidents.

Link to a time lapse video of the final shutdown.